CLIENTS

SC OMV PETROM  SA 

download.png

1. Execution of demolition, remediation / decontamination and ecological reconstruction

works on the sites related to the wells belonging to OMV PETROM, located in the counties -

Satu Mare, Salaj, Bihor, Arad, Timis, Maramures, Mures, Bistrita Nasud, Sibiu, Alba, Cluj,

Caras Severin, between 2012 - 2015

 

Technological processes:

  • ex-situ bioremediation technological process – 22.530 tons

  • inertization technological process – 8.780 tons

  • technological process for concrete decontamination – 3.600 tons

 

2. Cleaning / stripping / collecting, loading, transport, unloading of contaminated soil and

filling with clean soil, between 2012 -2017 - 30.000 tons

 

3. Collection, transport and recovery / final disposal services for hazardous / non-hazardous

drilling waste from OMV PETROM E&P locations, between 2014 - 2017

 

Technological processes:

  • technological process of sludge dehydration – 24.850 tons

  • inertization technological process – 10.400 tons

  • centrifugation technological process – 5.580 tons

 

4. Cleaning, emptying, slam processing, filling and ecological reconstruction of the site Slam

Cell Parc 1 Marca, Marca Commune, Jud. Salaj, between 2015-2017

 

Technological processes:

  • thermal desorption technological process – 65.800 tons

 

5. Works related to the abandonment of the wells belonging to OMV PETROM SA, between

2015 -2019

 

Technological processes:

  • ex-situ bioremediation technological process – 36.420 tons

  • inertization technological process – 2.720 tons

  • technological process for concrete decontamination – 4.120 tons

 

6. Execution of remediation, decontamination and ecological reconstruction works at the

site of former SIBIU Petroleum Products Warehouse - 2019

 

Technological processes:

  • on-site bioremediation technological process – 4.490 tons

  • in-site bioremediation technological process – 13.200 tons

  •  

7. Execution of remediation, decontamination and ecological reconstruction works at the

Site of former BEIUS Petroleum Products Warehouse - 2019

 

Technological processes:

  • ex-situ bioremediation technological process – 1.350 tons

 

8. Execution of remediation, decontamination and ecological reconstruction works at the

site of former Petroleum Products Warehouse SALONTA - 2019

 

Technological processes:

  • ex-situ bioremediation technological process – 1.200 tons

  • in-site bioremediation technological process – 2.880 tons

 

9. Execution of remediation, decontamination and ecological reconstruction works at the

site of former VASCAU Petroleum Products Warehouse —2019

 

Technological processes:

  • on-site bioremediation technological process – 4.920 tons

  • in-site bioremediation technological process – 12.432 tons

 

10. Execution of remediation, decontamination and ecological reconstruction works at the

site of former ALBA IULIA Petroleum Products Warehouse – 2019

 

Technological processes:

  • ex-situ bioremediation technological process – 7.255 tons

  • in-site bioremediation technological process – 4.520 tons

  •  

11. Execution of remediation, decontamination and ecological reconstruction works at the

site of former TITAN Petroleum Products Warehouse - 2020

 

Technological processes:

  • on-site bioremediation technological process – 29.829 tons

  • in-situ bioremediation technological process – 14.112 tons

  • ex-situ bioremediation technological process – 6.878 tons

 

12. Execution of remediation, decontamination and ecological reconstruction works at the

site of former SUCEAVA Petroleum Products Warehouse - 2021

 

Technological processes:

  • on-site bioremediation technological process – 19.800 tons

  • technological process bioremediation in-situ – 18.455 tons

  • ex-situ bioremediation technological process – 7.824 tons

PETROSANTANDER ROMANIA SRL

images.png
  1. Greening, collection, treatment, transport and final disposal of hazardous and non-hazardous waste and response in case of accidental pollution - 2014-2018; 2018-2022
    Technological processes:
    - technological process of centrifugation 5,000 tons
    - technological process of inerting 4,000 tons

       - technological process of decontamination of concrete 1,000 tons

M-I PETROGAS SERVICES ROMANIA SRL

societate care face parte din grupul SCHLUMBERGER

1. Location and logistics works Fluid station and greening works

 

2. Greening/cleaning, transport and final disposal of hazardous waste from OMV PETROM reservoirs production area 1 Crișana- Banat and production area 2 Oltenia.

 

3. Collection works, transport and final disposal of non-hazardous waste such as drilling mud based on fresh water - Parc 5 Marghita.

 

4. Construction and rental of a mixed station for preparation and treatment of drilling fluids - Suplacu de Barcău.

SC VIVANI SALUBRITATE SA

SC FARCAS-RO-TRANS SRL

Works within the projects for greening the oil sludge battles belonging to OMV PETROM, from the western part of Romania - Lot I, S.C. STILO EVORA S.R.L. has been the main partner as a provider of logistics, construction and construction assembly services. This greening project is the largest within PETROM, at the same time being a pioneering project in Romania.

 

1. Excavation and transport of hazardous waste Abraham Abram from OMV PETROM:
- technological process of thermal desorption 30,000 tons

 

2. Excavation and transport of hazardous waste at Turnu Arad within OMV-PETROM:
- technological process of thermal desorption 9,000 tons

 

3. Excavation and transport of hazardous waste battalion Park 30 Suplac within OMV- PETROM: - technological process thermal desorption 13,000 tons

 

4. Excavation and transport of hazardous waste Battle Park 1 and 2 Suplac within OMV- PETROM:
- technological process of thermal desorption 250,000 tons

 

5. Construction of the platform for the Thermal Desorption Installation (TDU) Suplacu de Barcău (surface 12,000sqm);

 

6. Execution of access roads to the Suplac TDU platform;

NIS PETROL SRL 
GASPROM member

1. Contract on waste management, transport and disposal - 2014-2021

EXPERT PETROLEUM

1. Greening, collection, treatment, transport and final disposal services for hazardous and non-hazardous waste and response in case of accidental pollution - 2014 -2022

ASTALDI-FCC-SALCEF-THALES MERGER

  1. Rehabilitation of the Border-Curtici-Simeria railway line, part of the Pan-European Corridor IV for trains running at a maximum speed of 160 km / h: Section 2: km 614 - Gurasada, sub- section 2b: Cap Y Bârzava - Cap Y Ilteu 2017 -2021
    Technological processes:
    - technological process bioremediation ex- situ / on-site 70,000 tons
    - technological process of inerting 1,000 tons
    - technological process of stone decontamination 100,000 tons
    - technological process of breaking and evacuating sleepers - 35,000 pieces

 

Also S.C. STILO EVORA S.R.L. an integral part of ALATAU ECOSERVICE carried out a pilot project in Kazakhstan, with the beneficiary KARAZHANBAS MUNAI S.A.

 

The Pilot Project involves the treatment of various types of petroleum waste with the Thermal Desorption Plant Type SDT-10M, in order to obtain IPOs for further activities in Kazakhstan.

In accordance with AGREEMENT NO 18KPP6-0897 / 07 06 2018 the following types and quantities of petroleum waste were subjected to processing:
· Waste of oil sludge from the polygon 100 tons · Waste drilling mud from the landfill 100 tons · Waste oil sludge / amber from amber 20 tons

 

The Pilot project for oil waste treatment with the Thermal Desorption Plant Type SDT-10M is completely completed, the entire amount of waste was processed in accordance with the technical specifications of the plant, the results corresponding to international and European standards and indicators.